RM Solar S Class 20 Manual de instrucciones Pagina 51

  • Descarga
  • Añadir a mis manuales
  • Imprimir
  • Pagina
    / 68
  • Tabla de contenidos
  • MARCADORES
  • Valorado. / 5. Basado en revisión del cliente
Vista de pagina 50
51 52
7.11 Finally the panels should be secured to the frame using the wind clamps. Position
the wind clamps at the top and bottom in the centre of each panel.
7.12 When the panels are connected together and the pipe work is complete the system
should be pressure tested to 6 bar using either compressed air or RM Solar glycol,
vented, and checked for leaks, and lled with the water/glycol mix. If you are tting
an in roof system, do the pressure test before you t the top and side ashings. For
lling instructions see part 14 of these instructions.
Note:
S Class M Class Econ
Max In A Row 3 10 5
Number Of Inlets 2 at top 1 each corner 1 each corner
Temperature Sensor Top Right Top Right On Air Vent
Vista de pagina 50
1 2 ... 46 47 48 49 50 51 52 53 54 55 56 ... 67 68

Comentarios a estos manuales

Sin comentarios